Some figures when considering the cost of work needed to complete the Hostel building (I will give them in GB Pounds, not Ugandan shillings):
Doors and windows: £3,102
Water tank and gutters: £1,379
Electrics, including solar panel: £3,033
Converting pit latrine to septic tank (see picture): £582.

Total for these items: £8,096
But there is more needed - notably concreting the floor, and rendering the walls inside and out, which is a substantial task.
The Committee will be considering how much of this work needs to be complete before the children can start to sleep there; and also what the priorities are.